A step-by-step guide for owner builders and builders
Fitting new windows and doors into a new build is one of the more satisfying milestones of a project, but only when the timing lines up with everything else on site. This guide walks owner builders and builders through the Premier process from first quote to final handover, so you know exactly what happens at each stage, when each payment falls due, and what we need from you to keep the job on track.
The whole journey is built around a 15-week production lead time. Knowing where that window sits against your slab, frame and lock-up dates is the single best thing you can do to avoid delays.
Every window and door we make is custom made to your project, there are no standard sizes. Each item is manufactured to the dimensions confirmed at your check-measure and signed off on your drawings, which is what allows them to fit your openings precisely.
The process at a glance
| STEP | STAGE | TIMING | WHAT HAPPENS / PAYMENT |
|---|---|---|---|
| 1 | Design & drawings | Pre-build | Showroom visit and free quote; choose products for practicality, efficiency and cost. Apply for your building permit. |
| 2 | Building permit issued | Week 0 | Order placed and deposit paid (Payment 1) — this secures your 15-week production slot. |
| 3 | Slab pour → frame / brickwork | Build underway | Openings are formed and the production lead time begins. |
| 4 | Structure up | ~Week 8 | Site survey / check-measure if required — important for double brick. |
| 5 | Approve each item | Week 9 | Review and sign off drawings for accuracy (Payment 2). Sign-off starts the 6-week call-off. |
| 6 | Build continues on site | Weeks 9-15 | 6-week call-off — fabrication, made to your signed-off sizes. |
| 7 | Site ready for install | Week 15 | Delivery and installation (or supply only) by Premier's in-house team (Payment 3, before installation). |
| 8 | Approaching completion | Before handover | Screens called off and fitted any time before handover (Payment 4, on completion). |
Please note: the weeks above are an example only. Every build runs to its own program, and we flex the delivery plan to fit yours — bring us your dates and we’ll map the production and install around your specific build.
Timing and lead times
Everything starts when you place your order and pay your deposit, which we call Week 0. That deposit secures a 15-week production slot, so the earlier you order, the more certainty you have over your install date.
Two timing milestones matter most. The first is the check-measure at around Week 8, once your structure is up and the openings are ready to measure. The second is drawings sign-off at Week 9, which kicks off a 6-week call-off into fabrication. From there, delivery and installation land at Week 15.
Because your windows and doors are made to your signed-off sizes, the clock on fabrication only starts once you approve the drawings. Sitting on the sign-off pushes everything downstream, so treating it as a priority keeps your install date firm.
The payment schedule
| PAYMENT | AMOUNT | WHEN | COVERS |
|---|---|---|---|
| Payment 1 - Deposit | 30% | At order (Week 0) | Secures your 15-week production slot |
| Payment 2 - Sign-off | 30% | At drawings sign-off (Week 9) | Releases your job into the 6-week call-off |
| Payment 3 - Installation | 30% | Before installation (Week 15) | Delivery and fitting by our in-house team |
| Payment 4 - Completion | 10% | On completion | Final stage including screens |
What we need from you
Keeping the process smooth comes down to a few things on your side:
- Plans and your energy report. To quote, all we need are your plans — ideally construction drawings — together with your energy report. We don’t need a building permit. This information tells us the window and glass specification to quote so your build achieves 7 stars, and (unless it’s a supply-only job) how we plan to install.
- Formed openings. As the slab is poured and frame or brickwork goes up, the openings are formed. Accurate openings are what we measure against.
- Walls up for the check-measure. Unlike the traditional way of installing aluminium windows, Premier uPVC windows don’t come with a subframe. That means the walls need to be up before we can check-measure — we measure directly to the finished openings. At around Week 8, once the structure is up, we need access to survey and measure. This step is vital for double brick, where final sizes can differ from the plans.
- Prompt drawings sign-off. Reviewing and approving each item at Week 9 is what releases your job into fabrication. The faster you sign off, the more reliably you hit Week 15.
- A site that’s ready for install. By Week 15 the openings need to be ready for our team to fit on site.
Why build with Premier
We make the process simple, transparent and stress-free at every step. A few things set us apart for new builds:
- In-house installation. Your windows and doors are fitted on site by Premier’s own team, not subcontracted out, so quality and accountability stay with us.
- Double-brick expertise. Our check-measure process is built for the realities of double brick, where measuring off plans alone risks costly errors.
Transparent staging. Clear stages and a defined payment schedule mean no surprises on timing or cost. - Energy efficiency. We help you choose products that balance practicality, efficiency and cost, so the result performs as well as it looks.
Ready to start?
The best first step is a showroom visit and a free, no-obligation quote. Bring your plans and we’ll help you choose the right products and map your 15-week window against your build program. Visit premierwindows.com.au to book.