The Premier Order Process

A step-by-step guide for owner builders and builders

Fitting new windows and doors into a new build is one of the more satisfying milestones of a project, but only when the timing lines up with everything else on site. This guide walks owner builders and builders through the Premier process from first quote to final handover, so you know exactly what happens at each stage, when each payment falls due, and what we need from you to keep the job on track.

The whole journey is built around a 15-week production lead time. Knowing where that window sits against your slab, frame and lock-up dates is the single best thing you can do to avoid delays.

Every window and door we make is custom made to your project, there are no standard sizes. Each item is manufactured to the dimensions confirmed at your check-measure and signed off on your drawings, which is what allows them to fit your openings precisely.

The process at a glance

STEPSTAGETIMINGWHAT HAPPENS / PAYMENT
1Design & drawingsPre-buildShowroom visit and free quote; choose products for practicality, efficiency and cost. Apply for your building permit.
2Building permit issuedWeek 0Order placed and deposit paid (Payment 1) — this secures your 15-week production slot.
3Slab pour → frame / brickworkBuild underwayOpenings are formed and the production lead time begins.
4Structure up~Week 8Site survey / check-measure if required — important for double brick.
5Approve each itemWeek 9Review and sign off drawings for accuracy (Payment 2). Sign-off starts the 6-week call-off.
6Build continues on siteWeeks 9-156-week call-off — fabrication, made to your signed-off sizes.
7Site ready for installWeek 15Delivery and installation (or supply only) by Premier's in-house team (Payment 3, before installation).
8Approaching completionBefore handoverScreens called off and fitted any time before handover (Payment 4, on completion).

Please note: the weeks above are an example only. Every build runs to its own program, and we flex the delivery plan to fit yours — bring us your dates and we’ll map the production and install around your specific build.

Timing and lead times

Everything starts when you place your order and pay your deposit, which we call Week 0. That deposit secures a 15-week production slot, so the earlier you order, the more certainty you have over your install date.

Two timing milestones matter most. The first is the check-measure at around Week 8, once your structure is up and the openings are ready to measure. The second is drawings sign-off at Week 9, which kicks off a 6-week call-off into fabrication. From there, delivery and installation land at Week 15.

Because your windows and doors are made to your signed-off sizes, the clock on fabrication only starts once you approve the drawings. Sitting on the sign-off pushes everything downstream, so treating it as a priority keeps your install date firm.

The payment schedule

Payments are staged across the build so you only pay as the job progresses – 30% deposit, 30% at sign-off, 30% at installation and 10% on completion:
PAYMENTAMOUNTWHENCOVERS
Payment 1 - Deposit30%At order (Week 0)Secures your 15-week production slot
Payment 2 - Sign-off30%At drawings sign-off (Week 9)Releases your job into the 6-week call-off
Payment 3 - Installation30%Before installation (Week 15)Delivery and fitting by our in-house team
Payment 4 - Completion10%On completionFinal stage including screens
Staging payments this way keeps your cash flow aligned with the build and means each milestone is tied to real progress, not an arbitrary date.

What we need from you

Keeping the process smooth comes down to a few things on your side:

  • Plans and your energy report. To quote, all we need are your plans — ideally construction drawings — together with your energy report. We don’t need a building permit. This information tells us the window and glass specification to quote so your build achieves 7 stars, and (unless it’s a supply-only job) how we plan to install.
  • Formed openings. As the slab is poured and frame or brickwork goes up, the openings are formed. Accurate openings are what we measure against.
  • Walls up for the check-measure. Unlike the traditional way of installing aluminium windows, Premier uPVC windows don’t come with a subframe. That means the walls need to be up before we can check-measure — we measure directly to the finished openings. At around Week 8, once the structure is up, we need access to survey and measure. This step is vital for double brick, where final sizes can differ from the plans.
  • Prompt drawings sign-off. Reviewing and approving each item at Week 9 is what releases your job into fabrication. The faster you sign off, the more reliably you hit Week 15.
  • A site that’s ready for install. By Week 15 the openings need to be ready for our team to fit on site.

Why build with Premier

We make the process simple, transparent and stress-free at every step. A few things set us apart for new builds:

  • In-house installation. Your windows and doors are fitted on site by Premier’s own team, not subcontracted out, so quality and accountability stay with us.
  • Double-brick expertise. Our check-measure process is built for the realities of double brick, where measuring off plans alone risks costly errors.
    Transparent staging. Clear stages and a defined payment schedule mean no surprises on timing or cost.
  • Energy efficiency. We help you choose products that balance practicality, efficiency and cost, so the result performs as well as it looks.

Ready to start?

The best first step is a showroom visit and a free, no-obligation quote. Bring your plans and we’ll help you choose the right products and map your 15-week window against your build program. Visit premierwindows.com.au to book.

Last updated: August 11, 2026

Table of Contents

Share this post

Some areas we serve

Download a free energy efficiency checklist for your home

BOOK A SHOWROOM VISIT

Premier Windows Balcatta showroom exterior for uPVC double glazing in Perth WA

PERTH SHOWROOM

20 Gibberd Road,
Balcatta,
WA 6021

SOUTHWEST SHOWROOM

By Appointment 12A Commerce Road, Vasse, 6280

Request A Quote

THE PREMIER SPECIFIER & PERFORMANCE MANUAL

Premier Windows uPVC windows & doors technical specification manual – Western Australia
Your essential guide to uPVC windows and doors in Western Australia.

Explore detailed technical specifications, installation methods, BAL ratings, energy performance, and finishing options, all in one place.

As a homeowner, this manual helps you design with confidence and avoid costly mistakes.

Receive our brochure

Brochure for Premier UPVC windows and doors

Discover the perfect blend of design and functionality in our brochure.

Get inspired by our frame finishes and the benefits of UPVC double glazing.

Fill out the form and receive a copy directly to your inbox.

Your Free Consultation

Choose the option that suits you best – visit a Premier Showroom and Design Centre or arrange a home consultation.

20 Gibberd Road, Balcatta, WA 6021

12a Commerce Road, Vasse, 6280

Over 500 WA homeowners visited us last year – book your free appointment today.
Premier Windows and Doors company logo for Australian double glazed windows and doors branding